PEPL Non-Critical Notice

Notice ID: 27366
Notice Type: PSO
Critical: N
Notice Status Description:
Reqrd Rsp Desc: No Response Required
Posting Date/Time: 2022-03-04 09:03:00.0
Subject: PEPL 2022 Pipeline Outage and Maintenance Summary
Notice Effective Date/Time: 2022-03-04 09:03:00.0
Notice End Date/Time: 2200-01-01 23:59:00.0
Notice Text:

Updated as of

2/20/2023

Listed below is a summary of the planned outages that could affect capacity or impact any receipt/delivery locations during the PEPL  2023 outage season.  This schedule is not a complete list of all outages and is subject to change as the season progresses to reflect any project delays, cancellations or additions.  Additionally, anticipated impact and restrictions are subject to change.  
*All scheduled dates represent gas days as defined in the PEPL Tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).

Start Date

End Date

Location

Unit(s)

Maintenance

Anticipated Impact

Meter(s) Impact

03/14/22

03/18/22

Greensburg

200 Line

Pipe Replacement

No impact to shippers expected

Black Hills Taps may see reduced pressure, Superior # 41417 will be shut-in

03/14/22

03/16/22

Greensburg

100 Line

Pipe Replacement

No impact to shippers expected

Black Hills Taps may see reduced pressure, Superior # 41417 will be shut-in

04/21/22

04/22/22

Sooner

16" Line

Anomaly Dig

Capacity through Sooner Line limited. Meters subject to scheduling reductions.

Meters 10632 DCP Kingfisher & 41433 Enlink Chisholm plt will need to be Shut-in

05/13/22

05/26/22

Liberal

200 Line

Valve Replacement

No impact to shippers expected

Black Hills Farm Taps, 41436, 13240 will be shut-in

05/23/22

05/27/22

Seiling

Meter 02428

Meter Upgrade

No impact to shippers expected

Meter 02428 will be Shut-in

07/06/22

08/19/22

Glenarm

Galesburg 100

Hydrotest

No impact to shippers expected

Meters 02098 & 02200 to be shut-in

07/25/22

08/05/22

Centralia

AP Green Lateral

Hydrotest & Tool Run

No impact to shippers expected

Meter 02601 will be shut-in

08/15/22

08/19/22

S. Elk City

22" Line

Valve Replacement

Capacity through South Elk City Line may be limited. Meters subject to scheduling reductions.

Meters 40466 & 12744 will be shut-in

8/25/2022

8/26/2022

Liberal

100 Line

Valve Replacement

No impact to shippers expected

Meter 41409 will be shut-in

9/7/2022

9/10/2022

Sneed

200 Line

Valve Replacement

Flow through a portion of the  Sneed 200 Line will not be available

Meters #12724, #41090 will be shut-in & Meter #13852 may experience higher pressures during this outage.

9/13/2022

9/15/2022

Tallgrass Grant

Meter 09222/09223

Meter Upgrades

No impact to shippers expected

Meter #09222 & 09223 will be shut-in

9/19/2022

10/4/2022

Sunray

100 Line

Wireline And Valve Replacement

Flow through Sunray Station will not be available

Meters #40524, #06228, #07430, #09099, #12840, will be shut-in

12/7/2022

12/7/2022

Greensburg

100 Line

Valve Replacement


Meter subject to scheduling reductions.

Location: NNATL