PEPL Critical Notice

Notice ID: 38631
Notice Type: MAI
Critical: Y
Notice Status Description:
Reqrd Rsp Desc: No Response Required
Posting Date/Time: 2023-09-05 08:59:00.0
Subject: National Helium Plant Turnaround
Notice Effective Date/Time: 2023-09-05 08:59:00.0
Notice End Date/Time: 2200-01-01 00:00:00.0
Notice Text:

9/5/2023  National Helium Plant Turnaround

 

DCP Midstream has scheduled its annual National Helium Plant turnaround to begin on Gas Day September 12, 2023. During the entirety of the turnaround, processing will be shut down and the Btu content of gas downstream of NHC will increase. In addition, dehydration will be shut down September 12th-20th, 2023.  Panhandle will be monitoring the water content of receipt points upstream of NHC. Expected duration of the plant outage is 14 days.

 

Updates to this maintenance schedule will be posted as they become available.

 

If you have any questions, please contact your Marketing or Customer Service Representative.