PEPL Non-Critical Notice

Notice ID: 8206
Notice Type: PSO
Critical: N
Notice Status Description:
Reqrd Rsp Desc: No Response Required
Posting Date/Time: 2019-03-05 10:44:00.0
Subject: PEPL 2019 Pipeline Outage and Maintenance Summary
Notice Effective Date/Time: 2019-03-05 10:44:00.0
Notice End Date/Time: 2021-01-01 06:00:00.0
Notice Text: LINK Bulletin Board - modified 10/27/93

Updated as of:

12/19/19

 

 

 

 

 

 

Panhandle Eastern Pipe Line 2019 Outage and Maintenance Summary

Listed below is a summary of the planned outages that could affect capacity or impact any receipt/delivery locations during the PEPL 2019 outage season. This schedule is not a complete list of all outages and is subject to change as the season progresses to reflect any project delays, cancellations or additions. Additionally, anticipated impact and restrictions are subject to change.
*All scheduled dates represent gas days as defined in the Panhandle tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).

*Indicates revision

 

 

 

 

 

 

Revised

Start Date

End Date

Location

Unit(s)

Maintenance

Anticipated Impact

Meter Impact

*

03/20/2019

03/23/2019

Haven

200 Line

Coupling Reinforcements

Mid Continent - Burns (09225) out of service

Location(s) #09225 shut-in

 

03/25/2019

03/29/2019

Tuscola

400 Line

Anomaly Dig

MGT Scotland (09248) out of service

Location #09248 shut in

 

04/01/2019

04/05/2019

Houstonia

Columbia Lateral

Sleeves

20% Pressure Reduction

Ameren's Siding/UM Power PLants (09239) Meter Out of Service; Location #UNELE Deduct

 

04/02/2019

04/05/2019

Zionsville

Defiance Stn

ILI Tool Run

Richland Power Plant (02853) out of service

Location #02853 shut in

 

04/08/2019

04/12/2019

Hansford

100 Line

Recoat

No Impact to Shippers Expected

None

 

04/15/2019

04/17/2019

Houstonia

400 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

04/23/2019

04/23/2019

Cashion

Station

ESD

4 hour ESD

Locations #10632 shut in during ESD

 

04/29/2019

05/04/2019

Hansford

200 Line

Pipe Replacement

Hansford Hinshaw 200 - DCP and OPTIMA out of service

Locations #41416 and #OPTMA shut in

 

04/30/2019

04/30/2019

Centralia

Station

ESD

No Impact to Shippers Expected

None

 

05/01/2019

05/01/2019

Seiling

Station

ESD

4 hour ESD

Locations in ELK City area. including locations #02428 and # 09069.

 

05/01/2019

05/01/2019

Greensburg

100 Line

Tool Run

No Impact to Shippers Expected

None

 

05/06/2019

05/17/2019

Zionsville

300 Lines

Citizens M&R Upgrade

No Impact to Shippers Expected

None

 

05/06/2019

06/14/2019

Pleasant Hill

200 Line

Sleeves/Pipe Replacements

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

05/07/2019

05/07/2019

Greensburg

Station

ESD

Northern Natural Meter location NNATL

Location #NNATL

 

05/08/2019

05/08/2019

Houstonia

300 Line

Tool Run

No Impact to Shippers Expected

None

 

05/08/2019

05/09/2019

Centralia

400

Valve Repair

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

05/09/2019

05/17/2019

Zionsville

200 Line

Citizens M&R Upgrade

No Impact to Shippers Expected

None

 

05/15/2019

05/15/2019

Houstonia

300 Line

Tool Run

No Impact to Shippers Expected

None

 

05/20/2019

05/20/2019

Liberal

Station

ESD

No Impact to Shippers Expected

None

 

05/22/2019

05/22/2019

Louisburg

300 Line

Tool Run

System Capacity impact

None

 

05/22/2019

05/25/2019

Liberal

100 Line

Check Valve Installation

Meters 41409 shut in

Location #41409 shut in

 

05/23/2019

05/24/2019

Olpe

200 Line

Pipe Reinforcement

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

05/28/2019

06/17/2019

Centralia

300

Hydrotest

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

06/04/2019

06/28/2019

West Line 100

Lateral

Anomaly Digs

No Impact to Shippers Expected

None

 

06/04/2019

07/19/2019

Zionsville

200 Line

SCC Spike test

Meter 02530 shut in 7/1 Meter 02795 shut in 7/8-7/10 Meter 02861 shut in 7/12-7/15

Location # 02530 shut in 7/1 Location # 02795 shut in 7/8-7/10 Location # 02861 shut in 7/12-7/15

 

06/10/2019

06/14/2019

Houstonia

100 line

Pipe replacement

No Impact to Shippers Expected

None

 

06/10/2019

06/21/2019

Houstonia

100 Line

Pipe Replacement

No Impact to Shippers Expected

None

 

06/17/2019

06/17/2019

Lakin

100 Line

Tool Run

No Impact to Shippers Expected

None

 

06/18/2019

06/21/2019

Houstonia

100 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

06/18/2019

07/02/2019

Centralia

200

Relays

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

06/20/2019

06/20/2019

Satanta

100 Line

Tool Run

No Impact to Shippers Expected

None

*

06/24/2019

07/02/2019

Olpe

100 Line

Tool Run

No Impact to Shippers Expected

None

 

06/24/2019

07/13/2019

Centralia

100 Line

Relays

No Impact to Shippers Expected

None

 

07/02/2019

07/24/2019

Centralia

200

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

07/08/2019

07/12/2019

Houstonia

100 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

 

07/15/2019

07/19/2019

Houstonia

100 Line

Wireline

No Impact to Shippers Expected

None

 

07/17/2019

07/17/2019

Liberal

100 Line

Tool Run

Reduced Pressure; Capacity on the Liberal 100 Line will be limited . IT nominations are subject to scheduling reductions

Location #41409 limited for 12 hours

*

07/17/2019

07/17/2019

Houstonia

Station

ESD

No Impact to Shippers Expected

None

 

07/22/2019

08/02/2019

Houstonia

200 Line

Sleeves & Couplings

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

 

07/22/2019

08/12/2019

Canton

Lateral

Hydrotest

No Impact to Shippers Expected

None

 

07/23/2019

08/06/2019

Olpe

200 Line

Pipe Reinforcement

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

 

07/23/2019

08/15/2019

Olpe

200 Line

Anomaly Repairs

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

 

07/22/2019

08/01/2019

Houstonia

200 Line

Pipe Replacement

No Impact to Shippers Expected

None

 

07/22/2019

08/01/2019

Houstonia

200 Line

Pipe Replacement

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

 

07/22/2019

08/01/2019

Houstonia

200 Line

Sleeves

No Impact to Shippers Expected

None

 

08/12/2019

08/16/2019

Pleasant Hill

300 Line

Sleeves/Pipe Replacements

No Impact to Shippers Expected

None

 

08/12/2019

08/17/2019

Pleasant Hill

300 Line

Sleeves

No Impact to Shippers Expected

None

 

08/12/2019

08/18/2019

Haven

200/300 Lines

Valve Installation

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

*

09/05/2019

09/05/2019

Olpe

400 Line

Tool Run

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

 

09/05/2019

09/11/2019

Haven

300 Line

Check Meter Retirement

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

 

09/09/2019

09/13/2019

Seiling

100 Line

Relay

All Meters upstream from Seiling Station are limited to 0

All Meters upstream from Seiling Station are limited to 0

 

09/17/2019

09/17/2019

Tuscola

Station

ESD

No Impact to Shippers Expected

None

*

05/30/2019

09/24/2019

Louisburg

300 Line

Hydrotest

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

Location #PNYEX Shut in during outage

*

07/15/2019

09/20/2019

Cashion

Station

Unit 2302

DCP Kingfisher 10632 limited capacity

Location #10632 limited

 

10/21/2019

10/25/2019

Elk City

100 Line

Sleeves

Midcoast Pipelines Beckham County and Delhi Carpenter Receipt - WIT out of service

Locations #12744 and #41215 shut in

 

08/20/2019

09/30/2019

Houstonia

400 Line

Hydrotest

Capacity through Houstonia may be limited; IT and all secondary nominations are subject to scheduling reductions

none

 

09/30/2019

10/04/2019

Louisburg

200 Line

Sleeves

No Impact to Shippers Expected

None

*

10/08/2019

10/09/2019

Zionsville

First Energy 100 Line

Tool Run

Richland Power Plant out of service

Location #02853 shut in

 

10/14/2019

10/17/2019

Greensburg

100 Line

Pipe Replacement

Lerado Discharge out of service

Location #41044 shut in; Operators upstream of Valve Section 6 may experience higher than normal pressures

 

10/21/2019

10/24/2019

Hansford

100 Line

Pipe Replacement

Arkalon Energy

Locations #41383 shut in

 

09/23/2019

10/25/2019

Haven

300 Line

Hydrotest

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

 

10/01/2019

11/08/2019

Houstonia

300 Line

Relays

Capacity through Houstonia may be limited; IT and all secondary nominations are subject to scheduling reductions

None

*

07/22/2019

11/20/2019

Canton

Lateral

Canton M&R Ameren Upgrade

No Impact to Shippers Expected

None

*

07/29/2019

11/20/2019

Bartonville

Lateral

Hydrotest

No Impact to Shippers Expected

None

 

11/04/2019

11/16/2019

Montezuma

200 Line

Anomaly Digs

No Impact to Shippers Expected

None

 

11/11/2019

11/16/2019

Montezuma

200 Line

Anomaly Digs

No Impact to Shippers Expected

None

*

11/11/2019

11/29/2019

Tuscola

200 Line

Anomaly Digs

No Impact to Shippers Expected

None

 

11/18/2019

11/26/2019

Haven

300 Line

Check Meter Replacement

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

none

*

08/19/2019

11/26/2019

Woodson

Lateral

Woodson M&R Ameren Upgrade

No Impact to Shippers Expected

None

 

10/28/2019

11/27/2019

Zionsville

100 Line

Relay

No Impact to Shippers Expected

None