PEPL Non-Critical Notice

Notice ID: 8720
Notice Type: PSO
Critical: N
Notice Status Description:
Reqrd Rsp Desc: No Response Required
Posting Date/Time: 2020-07-23 16:09:00.0
Subject: PEPL 2020 Pipeline Outage and Maintenance Summary
Notice Effective Date/Time: 2020-07-23 16:09:00.0
Notice End Date/Time:
Notice Text: LINK Bulletin Board - modified 10/27/93


 

 

Updated as of

 

12/20/2020

 

 

 

 

Listed below is a summary of the planned outages that could affect capacity or impact any receipt/delivery locations during the PEPL 2020 outage season. This schedule is not a complete list of all outages and is subject to change as the season progresses to reflect any project delays, cancellations or additions. Additionally, anticipated impact and restrictions are subject to change.
*All scheduled dates represent gas days as defined in the PEPL Tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).

 

 

 

 

 

 

 

Start Date

End Date

Location

Unit(s)

Maintenance

Anticipated Impact

Meter(s) Impact

12/10/2019

3/27/2020

Tuscola

200 Line

Sleeves

No impact to shippers expected

None

3/9/2020

3/12/2020

Louisburg

300 Line

Anomaly Dig

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

3/10/2020

3/17/2020

Tuscola

200 Line

Anomaly Dig

No impact to shippers expected

None

3/12/2020

8/1/2020

Olpe

200 Line

Anomaly Digs

Reduction in Line Pressure

None

3/17/2020

4/3/2020

Houstonia

100 Line

Sleeves & Couplings

No impact to shippers expected

None

3/17/2020

4/3/2020

Centralia

200 Line

Pipe Replacement

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

3/24/2020

3/24/2020

Montezuma

300 Line

ILI Tool Run

No impact to shippers expected

None

3/26/2020

3/27/2020

Montezuma

300 Line

ILI Tool Run

No impact to shippers expected

None

4/1/2020

4/2/2020

Louisburg

200 Line

Sleeves & Couplings

No impact to shippers expected

None

4/1/2020

4/3/2020

Houstonia

200 line

Leak Repair

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

4/2/2020

4/22/2020

Montezuma

300 Line

Hydrotest

No impact to shippers expected

None

4/6/2020

4/15/2020

Olpe

100 Line

Sleeves & Couplings

No impact to shippers expected

None

4/6/2020

4/9/2020

Houstonia

200 Line

Sleeves & Couplings

No impact to shippers expected

None

4/6/2020

5/9/2020

Glenarm

200 Line

Anomaly Dig

No impact to shippers expected

None

4/6/2020

4/20/2020

Centralia

200 Line

Pipe Replacement

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

4/7/2020

4/7/2020

Houstonia

Station

ESD

No impact to shippers expected

None

4/8/2020

6/12/2020

Zionsville

Station

M&R Upgrade

No impact to shippers expected

Vectren Meter # 02796 will be shut-in

4/14/2020

4/14/2020

Tuscola

Station

ESD

No impact to shippers expected

None

4/14/2020

4/14/2020

Pleasant Hill

Station

ESD

No impact to shippers expected

None

4/15/2020

4/21/2020

Louisburg

200 Line

Anomaly Dig

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

4/20/2020

4/21/2020

Olpe

Unit 630

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

4/20/2020

5/11/2020

Centralia

200 Line

Sleeves

No impact to shippers expected

None

4/21/2020

4/22/2020

Edgerton

Freedom Line 100

Tool Run

No impact to shippers expected

None

4/21/2020

4/21/2020

Centralia

Station

ESD

No impact to shippers expected

None

4/22/2020

4/22/2020

Montezuma

Station

ESD

No impact to shippers expected

None

4/22/2020

4/24/2020

Olpe

Unit 631

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

4/23/2020

4/24/2020

Edgerton

Freedom Line 100

Tool Run

No impact to shippers expected

None

4/23/2020

4/23/2020

Haven

Station

ESD

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

4/27/2020

6/1/2020

Louisburg

400 Line

Hydrotest

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

4/28/2020

4/28/2020

Cashion

Station

ESD

Capacity through Cashion may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

Locations #10632 shut in during ESD

4/29/2020

5/13/2020

Montezuma

400 Line

Class Upgrade

No impact to shippers expected

None

5/5/2020

5/5/2020

Hopeton

Station

ESD

Capacity through Hopeton/Alva may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

Locations in Elk City Area

5/6/2020

5/9/2020

Hansford

100 Line

Pipe Replacement

Capacity through Hansford may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

Arkalon #41383 will be shut-in

5/7/2020

5/8/2020

Edgerton

WestLine 200

Tool Run

No impact to shippers expected

None

5/7/2020

5/8/2020

Olpe

200 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

5/11/2020

5/15/2020

Hansford

200 Line

Pipe Replacement

Capacity through Hansford may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

Plains location meter 13860 Shut in

5/11/2020

5/15/2020

Haven

100 Line

Pipe Replacement

No impact to shippers expected

None

5/11/2020

5/15/2020

Liberal

300 Line

Sleeves

No impact to shippers expected

None

5/11/2020

5/15/2020

Haven

100 Line

Casing Wireless project

No impact to shippers expected

None

5/11/2020

6/19/2020

Pleasant Hill

100 Line

Sleeves

No impact to shippers expected

None

5/13/2020

6/10/2020

Montezuma

400 Line

Pipe Replacement & Hydrotest

No impact to shippers expected

None

5/18/2020

5/22/2020

Olpe

100 Line

Casing Wireless project

No impact to shippers expected

None

5/21/2020

6/25/2020

Howell Storage

Station

Station Upgrades

No impact to shippers expected

None

5/26/2020

5/29/2020

Louisburg

100 Line

Pipe Replacement

No impact to shippers expected

None

5/26/2020

5/29/2020

Louisburg

100 Line

Pipe Replacement

No impact to shippers expected

None

5/27/2020

7/21/2020

Houstonia

200 Line

Hydrotest

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

5/27/2020

5/27/2020

Glenarm

Station

ESD

No impact to shippers expected

None

6/1/2020

6/4/2020

Pleasant Hill

100 Line

Sleeves & Couplings

No impact to shippers expected

None

6/1/2020

6/4/2020

Hansford

100 Line

Pipe Replacement

Capacity on the Hansford 100 Line may be limited

None

6/1/2020

6/10/2020

Haven

100 Line

Meter Removal

No impact to shippers expected

None

6/1/2020

6/5/2020

Greensburg

100 Line

Sleeves

No impact to shippers expected

None

6/2/2020

6/24/2020

Lee 8 storage

12" Line

Tool Run

No impact to shippers expected

None

6/2/2020

6/3/2020

Zionsville

400 Line

ILI Tool Run

No impact to shippers expected

None

6/2/2020

6/4/2020

Olpe

300 Line

Tool Run

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

6/3/2020

6/3/2020

Louisburg

Station

ESD

No impact to shippers expected

None

6/4/2020

6/5/2020

Zionsville

400 Line

ILI Tool Run

No impact to shippers expected

None

6/8/2020

6/20/2020

Montezuma

300 Line

Pipe Replacement & Hydrotest

No impact to shippers expected

None

6/8/2020

6/27/2020

Zionsville

400 Line

Pipe Replacement

No impact to shippers expected

None

6/10/2020

6/10/2020

Haven

400 Line

Tool Run

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

6/15/2020

6/19/2020

Edgerton

WestLine 100

Class Upgrade

No impact to shippers expected

None

6/15/2020

6/30/2020

Houstonia

300 Line

Hydrotest

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

6/17/2020

6/19/2020

Louisburg

200 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

6/22/2020

7/3/2020

Montezuma

200 Line

Pipe Replacement & Hydrotest

No impact to shippers expected

None

6/23/2020

6/24/2020

Lee 8 storage

12" Line

Tool Run

No impact to shippers expected

None

6/23/2020

7/17/2020

Pleasant Hill

400 Line

Hydrotest

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

6/30/2020

7/1/2020

Louisburg

300 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/6/2020

7/7/2020

Pleasant Hill

Unit 1018

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

6-Jul

10-Aug

Montezuma

200 Line

Pipe Replacement

No impact to shippers expected

None

7/6/2020

7/11/2020

Zionsville

100 Line

Pipe Replacment

No impact to shippers expected

None

7/6/2020

7/18/2020

Edgerton

WestLine 100

Hydrotest

No impact to shippers expected

None

7/6/2020

7/10/2020

Houstonia

200 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/6/2020

7/10/2020

Olpe

400 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/7/2020

7/10/2020

Louisberg

400 Line

Tool Run

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/8/2020

7/9/2020

Pleasant Hill

Unit 1019

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/8/2020

7/9/2020

Pleasant Hill

Unit 1019

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/13/2020

7/18/2020

Glenarm

Peoria Lateral

Valve Replacement

TBD

San Jose M&R meter #02231 shut-in

7/13/2020

7/14/2020

Haven

300 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/15/2020

7/15/2020

Olpe

Whole Station

ESD

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/15/2020

7/17/2020

Haven

200 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/20/2020

7/24/2020

Edgerton

200 Line

Anomaly Dig

No impact to shippers expected

None

7/20/2020

8/6/2020

Olpe

400 Line

Station Upgrades

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/20/2020

8/6/2020

Olpe

400 Line

Station Upgrades

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

7/20/2020

7/24/2020

Alva/ Hopeton

Whole Station

new control system installation

Capacity through Alva/Hopeton may be limited; IT and all secondary nominations are subject to scheduling reductions

Loctions in Elk City Area

7/20/2020

7/21/2020

Houstonia

200 Line

Sleeves

No impact to shippers expected

None

7/27/2020

7/30/2020

Edgerton

Maumee Lateral

Repair Control Valve

No impact to shippers expected

COLOH Shut in

8/3/2020

8/7/2020

Louisburg

Belton Lateral

Pipe Replacement

Anticipated Line outage

#01184 & #02191

8/3/2020

8/7/2020

Louisburg

State Line Lat

Pipe Replacement

Anticipated Line outage

#01184 & #02191

8/5/2020

8/5/2020

Howell Storage

Station

Station Upgrades

No impact to shippers expected

None

8/10/2020

8/15/2020

Edgerton

North Line 100

Sleeves & Couplings

No impact to shippers expected

None

8/10/2020

8/14/2020

Stateline Lateral

100 Lateral

Tool Run

No impact to shippers expected

None

8/10/2020

8/14/2020

Louisburg

State Line Lat

Pipe Replacement

Anticipated Line outage

#01184 & #02191

8/11/2020

8/11/2020

Louisburg

400 Line

Tool Run

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

7/27/2020

8/17/2020

Zionsville

200 Line

Anomaly Dig

No impact to shippers expected

None

8/10/2020

8/21/2020

Edgerton

North Line 100

Pipe Replacement

No impact to shippers expected

None

8/18/2020

8/18/2020

Hansford

Whole Station

ESD

No impact to shippers expected

None

8/18/2020

8/18/2020

Liberal

Whole Station

ESD

No impact to shippers expected

None

8/18/2020

8/18/2020

Satanta

Whole Station

ESD

No impact to shippers expected

None

8/17/2020

8/19/2020

Liberal

100 Line

Anomaly Digs

Anticipated Line outage

Meter #06204 Shut in

8/10/2020

8/21/2020

Louisburg

State Line Lat

Pipe Replacement

Anticipated Line outage

#01184 & #02191

8/19/2020

8/24/2020

Liberal

100 Line

Anomaly Digs

No impact to shippers expected

None

8/24/2020

8/27/2020

Houstonia

400 Line

Anomaly Digs

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

8/27/2020

8/28/2020

Olpe

100 Line

Anomaly Digs

No impact to shippers expected

None

8/27/2020

8/28/2020

Olpe

100 Line

Anomaly Digs

No impact to shippers expected

None

8/3/2020

9/4/2020

Glenarm

Peoria Lateral

Valve Replacement

No impact to shippers expected

None

8/11/2020

9/11/2020

Montezuma

300 lIne

Pipe Replacement

No impact to shippers expected

None

8/17/2020

9/4/2020

Zionsville

100 Line

Pipe Replacement

No impact to shippers expected

None

8/24/2020

8/26/2020

Louisburg

200 Line

Pipe Replacement

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

8/31/2020

9/3/2020

Olpe

300 Line

Pipe Replacement

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

8/31/2020

9/11/2020

Houstonia

300 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

8/21/2020

9/15/2020

Haven

400 Line

Anomaly Digs

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

9/3/2020

9/17/2020

Glenarm

400 Line

Hydrotest

Capacity through Tuscola may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

9/7/2020

9/16/2020

Edgerton

WestLine 100

Anomaly Dig

No impact to shippers expected

None

9/14/2020

9/15/2020

Liberal

200 Line

Sleeves

No impact to shippers expected

None

9/15/2020

9/18/2020

Liberal

200 Line

Sleeves

No impact to shippers expected

None

9/16/2020

9/17/2020

Haven

200 Line

Sleeves

No impact to shippers expected

None

9/16/2020

9/17/2020

Houstonia

200 Line

Sleeves

No impact to shippers expected

None

8/24/2020

9/26/2020

Glenarm

100 Line

Hydrotest

No impact to shippers expected

Mt. Zion & Friendship Hill segments

9/28/2020

10/10/2020

Edgerton

300 Line

Anomaly Dig

No impact to shippers expected

None

9/21/2020

9/22/2020

Houstonia

100 Line

Anomaly Digs

No impact to shippers expected

None

9/21/2020

9/25/2020

Centralia

300/400 Lines

Valve Replacement

Capacity through Haven may be limited; IT and all secondary nominations are subject to scheduling reductions

None

9/22/2020

9/24/2020

Edgerton

WestLine 200

Tool Re-Run

No impact to shippers expected

None

9/14/2020

10/3/2020

Edgerton

100 Line

Anomaly Dig

No impact to shippers expected

None

9/21/2020

10/3/2020

Glenarm

300 line

Pipe Replacement

No impact to shippers expected

None

9/23/2020

9/29/2020

Pleasant Hill

300 Line

Pipe Replacement

No impact to shippers expected

None

9/29/2020

9/29/2020

Edgerton

BP-PCS Lateral

Tool Run

No impact to shippers expected

None

9/30/2020

10/2/2020

Louisburg

200 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

10/1/2020

10/1/2020

Edgerton

BP-PCS Lateral

Tool Run

No impact to shippers expected

None

10/1/2020

10/2/2020

Houstonia

Jeff City Lateral

Anomaly Digs

May see a reduction in Line Pressure

02130, 02287, 09133

9/17/2020

10/7/2020

Sunray

Station

Repair Engine Surge Tank

location 40524 shut in

location 40524 shut in

9/14/2020

10/9/2020

Montezuma

200 Line

Pipe Replacement

No impact to shippers expected

None

9/28/2020

10/10/2020

Edgerton

300 Line

Anomaly Dig

No impact to shippers expected

None

10/5/2020

10/6/2020

Houstonia

200 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

10/6/2020

10/6/2020

Tuscola

Station

ESD

No impact to shippers expected

None

10/6/2020

10/7/2020

Centralia

Unit 921

Annual Inspection

No impact to shippers expected

None

10/7/2020

10/7/2020

Pleasant Hill

Station

ESD

No impact to shippers expected

None

10/8/2020

10/9/2020

Centralia

Unit 920

Annual Inspection

No impact to shippers expected

None

10/12/2020

10/13/2020

Pleasant Hill

Unit 1018

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

10/12/2020

10/14/2020

Edgerton

WestLine 200

Tool Re-Run

Reduction in Line Pressure

None

10/13/2020

10/13/2020

Borchers

100 Line

Tool Run

No impact to shippers expected

None

10/13/2020

10/16/2020

Hansford

100 Line

Pipe Replacment

Arkalon Meter 41383 Shut in

Arkalon Meter 41383 Shut in

10/14/2020

10/15/2020

Pleasant Hill

Unit 1019

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

10/14/2020

10/14/2020

Zionsville

Station

ESD

No impact to shippers expected

None

10/15/2020

10/15/2020

Borchers

100 Line

Tool Run

No impact to shippers expected

None

9/7/2020

10/17/2020

Zionsville

Station

M&R Upgrade

No impact to shippers expected

None

9/28/2020

10/17/2020

Glenarm

400 Line

Hydrotest

Capacity through Tuscola may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

10/12/2020

10/17/2020

Glenarm

200 Line

Pipe Replacement & Hydrotest

No impact to shippers expected

None

10/19/2020

10/21/2020

Olpe

Unit 630

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

10/20/2020

10/21/2020

Olpe

300 Line

Tool Run

No impact to shippers expected

None

10/22/2020

10/23/2020

Olpe

Unit 631

Annual Inspection

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

5/8/2020

10/30/2020

Tuscola

100 Line

Sleeves

No impact to shippers expected

None

10/19/2020

10/30/2020

Houstonia

200 Line

Hydrotest

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

10/26/2020

10/30/2020

Centralia

100 Line

Sleeves

No impact to shippers expected

None

10/26/2020

10/30/2020

Centralia

200 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

10/26/2020

10/30/2020

Montezuma

400 Line

Anomaly Digs

No impact to shippers expected

None

10/28/2020

10/28/2020

Montezuma

Station

ESD

No impact to shippers expected

None

11/4/2020

11/4/2020

Edgerton

Station

ESD

No impact to shippers expected

None

11/4/2020

11/4/2020

Liberal

400 Line

Hot Tap

No impact to shippers expected

None

11/4/2020

11/6/2020

Houstonia

300 Line

Anomaly Digs

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

11/2/2020

11/6/2020

Edgerton

200 Line

Pipe Replacement

TBD

TBD

11/4/2020

11/6/2020

Peoria

200 Line

Valve Replacement

No impact to shippers expected

Reduced pressure at the following M&Rs:
#02231 (San Jose), #02141 (Delavan), #02280 (Greenvalley)

11/5/2020

11/5/2020

Liberal

300 Line

Hot Tap

No impact to shippers expected

None

11/5/2020

11/5/2020

Liberal

300 Line

Hot Tap

No impact to shippers expected

None

10/29/2020

11/11/2020

Louisburg

300 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

11/9/2020

11/14/2020

Belton

100 Line

Sleeves

No impact to shippers expected

None

11/12/2020

11/19/2020

Louisburg

400 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

11/19/2020

11/24/2020

Louisburg

400 Line

Anomaly Digs

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

11/18/2020

11/20/2020

Houstonia

200 Line

Sleeves

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

11/30/2020

12/1/2020

Louisburg

100 line

Sleeves

No impact to shippers expected

None

12/1/2020

12/4/2020

Liberal

Liberal

100 Line

Anomaly Digs

Meter #41409 shut in

12/3/2020

12/8/2020

Olpe

200 Line

Anomaly Digs

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

12/7/2020

12/10/2020

Olpe

200 Line

Anomaly Digs

Capacity through Haven may be limited; IT and Secondary Out of Path nominations are subject to scheduling reductions

None

12/7/2020

12/10/2020

Houstonia

Jeff City Lateral

Farm tap retirements

No impact to shippers expected

None

12/9/2020

12/11/2020

Houstonia

100 line

Farm tap retirements

No impact to shippers expected

None

12/15/2020

12/16/2020

Louisburg

200 Line

Sleeves

No impact to shippers expected

None

12/16/2020

12/17/2020

Houstonia

Tipton Lateral

Farm tap retirements

No impact to shippers expected

None

12/16/2020

12/18/2020

Houstonia

Jeff City Lateral

Sleeves

No impact to shippers expected

None