| Notice Type Description: | Planned Service Outage |
| Notice Identifier: | 119960 |
| Critical Notice Description: | Critical notice |
| Posting Date/Time: | Aug 13 2026 12:12PM |
| Notice Status Description: | Initiate |
| Required Response Indicator Description: | No response required |
| Response Date/Time: | |
| TSP: | 7933047 |
| TSP Name: | TRANSWESTERN PIPELINE COMPANY, LLC |
| Subject: | Bloomfield Compressor Station Maintenance- 9/8 thru 9/18/26 |
| Notice Effective Date/Time: | Sep 8 2026 9:00AM |
| Notice End Date/Time: | Sep 19 2026 8:59AM |
|
Notice Text: Nominated Volume Affected |
August 13, 2026 To: All Transwestern Pipeline Customers Harvest Valverde capacity will be reduced from 230,000 MMBtu/d to zero.
|
| Reason: | Pipeline Maintenance |
| Location: | Bloomfield Compressor Station - Located on the San Juan Lateral |