FGT Critical Notice

Notice ID: 62491
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Mar 24 2026 1:21 PM
Subject: APRIL 2026 --- FGT WESTERN DIVISION AND MARKET AREA MAINTENANCE
Notice Effective Date/Time: Apr 1 2026 9:00 AM
Notice End Date/Time: May 1 2026 9:00 AM
Notice Text:

FGT will be performing pipeline maintenance on the mainlines between FGT Compressor Stations 6 and 7 in April. There is a potential for pipeline flow reductions during this maintenance.

FGT will be performing maintenance on its FGT Compressor Station 7. This maintenance begins on April 1, 2026, and will continue into May 2026. During this maintenance, FGT will schedule up to 375,000 MMBtu/day through Station 7. During normal operations, FGT schedules up to 465,000 MMBtu/day through Station 7.

FGT maintenance will continue at FGT Compressor Station 75. This maintenance is to be completed by the end of gas day April 18, 2026. During this maintenance FGT may continue to schedule up to 900,000 MMBtu/day through Station 75. During normal operations, FGT schedules up to 980,000 MMBtu/day through Station 75.

FGT will be performing maintenance at FGT Compressor Station 10. This maintenance will start April 13, 2026, and is to be completed by end of gas day April 16, 2026. During this maintenance FGT may schedule up to 1,100,000 MMBtu/day through Station 10. During normal operations, FGT schedules up to 1,300,000 MMBtu/day through Station 10.

FGT will continue maintenance downstream of FGT Compressor Station 12. This maintenance will continue through the end of April 2026. During this maintenance FGT may schedule up to 2,800,000 MMBtu/day through Station 12, During normal operations, FGT schedules up to 3,175,000 MMBtu/day through Station 12.